Home / Turnkey vs tolling
Turnkey vs tolling, explained with the money consequences
Turnkey, tolling or hybrid: who buys the materials, and what that does to the quote, your cash and the contract.
One decision: who buys the materials.
Turnkey and tolling describe one decision: who buys the materials. In a tolling deal you buy the ingredients, cans and packaging and the plant charges to run them. In a turnkey deal the plant buys them and sells you finished product at one price. A hybrid splits the list, for example your flavor and the plant’s cans.
Most guides stop there and say neither is better. They are right, and it is not much help. The difference shows up in three places. It shows up in the quote, because a low tolling fee next to a turnkey price is not the same question. It shows up in your cash, because you pay suppliers earlier under tolling. And it shows up in the contract: who owns leftover cans and ingredients after a run, what you owe if your materials arrive late, and what the plant adds on anything it buys for you.
Use the table below to compare the models on your own numbers before you ask for quotes. Ask each plant to price the same scope. If you already hold a quote and cannot tell which model it assumes, email it to ben@genwest.ventures. Our Co-Pack Quote & Contract Review is available starting at $1,500.
Not legal advice. We work alongside your attorney, and we will recommend one if you do not have one.
Tolling, turnkey and hybrid side by side.
Plants vary in what they offer, including ingredient sourcing and other support, so confirm what each one will handle.
| Tolling | Turnkey | Hybrid | |
|---|---|---|---|
| Who orders the materials | You order the ingredients, cans and packaging the plant will run. | The plant orders the materials its quote includes. | You and the plant each order specific items, agreed in writing before anyone buys. |
| What you pay the plant for | Production, plus any additional charges. | The agreed materials, production and any additional charges, in one price. | Production, the materials the plant buys, and any additional charges. |
| What you manage | Orders, supplier payments and deliveries for what you buy. | Product approvals, and any purchasing the plant does not cover. | Your supplier orders, and coordination with the plant’s purchasing. |
| What to confirm | The plant’s material requirements and delivery deadlines. | Which materials the plant buys, and what the quote leaves out. | Who orders each ingredient and each packaging item. |
Under any of the three, supplier minimums can leave you with unused ingredients or packaging. Confirm who pays for that inventory, where it is stored, and whether it can be used on the next run. A plant placing the order does not mean the plant absorbs what is left.
Structure based on JAI Development’s guide to tolling (Oct 28, 2026), written up here in our own words. The table scrolls sideways on a phone.
A low tolling fee next to a turnkey price is not the same question.
A tolling quote and a turnkey quote are priced for different jobs. A tolling fee covers the production work. A turnkey price also covers the cans, the ingredients and the purchasing. Put the two side by side and the tolling number will often look lower, because the other number has more in it. That is the question to settle first.
To compare fairly, add to the tolling quote everything the turnkey price already includes: ingredients, cans and ends, trays or carriers, and the freight to get each of them to the plant. Then add what you pay for leftovers and what your own time is worth. Then compare. How to read a co-packer quote has the line-by-line list.
JAI Development makes the same warning: confirm what each plant is supplying before you compare price.
Tolling means you pay suppliers earlier.
Tolling. You pay suppliers for ingredients and packaging before the run, and you hold that inventory until it is used. Bravo CPG describes laying out cash for ingredients well before they become finished goods and well before those goods become revenue. It also notes that managing a tolling operation takes real time from someone, tracking orders and inventory at the plant.
Turnkey. The plant carries the materials and prices that into what you pay. Bravo CPG says that is a premium, and that it buys you less cash tied up in raw materials and a more predictable cost of goods.
JAI Development notes that tolling can be cheaper if you have good supplier pricing and can manage purchasing well, and that you should weigh the cash needed before production and your team’s time against the savings. Both views are the authors’, and they point the same way: do the cash math, not just the unit math.
Sources: Bravo CPG, Turnkey vs Non-Turnkey (Tolling); JAI Development.
Which terms change with the model.
Three of the twelve terms in our contract terms guide change the most with the model:
- Turnkey or tolling (term 2): who buys what, the markup on materials the plant buys, and who owns what is left over.
- Downtime charges (term 3): what you owe if materials you buy arrive late, and what the plant owes you if it moves your slot.
- Inventory aging (term 7): how long materials and finished goods can sit before storage fees start or the loss becomes yours.
If you buy your own cans under tolling, you control the delivery date, so you are the one exposed to a downtime charge. If the plant buys them, you are exposed to the markup instead. Neither is free. The agreement decides how much each one costs.
Most brands change models as they grow.
Bravo CPG says most brands that start turnkey eventually move toward tolling as they scale, and puts the crossover at around $10 to $20 million in revenue. It also says turnkey usually makes sense for brands under roughly $5 million in revenue. Those are one operations firm’s views, not rules, and the trigger it names is capacity, not revenue: a team with the time, the cash and the inventory systems to run the supply chain.
The same source names exceptions. If your brand depends on a specific sourcing requirement the plant cannot match, owning that supply chain from day one can be the point.
A short checklist before you choose
- Who on your team will place, track and pay for material orders?
- Can you fund materials before the run, and carry them until they are used?
- Is your supplier pricing better than the plant’s, and can you prove it?
- Does your product need a sourcing requirement the plant cannot meet?
- Which model does each quote on your desk assume, and does it say so?
Before you ask for quotes, our co-packer RFP template asks whether you need turnkey service, along with volume, dates and who provides materials. The RFP checklist is the list of questions to work through first. For the money side, see what it costs to launch a canned beverage.
Source: Bravo CPG, Turnkey vs Non-Turnkey (Tolling). Read Nov 28, 2026.
Where this comes from.
- JAI Development, Tolling in Manufacturing: A Beverage Founder’s Guide, Oct 28, 2026.
- Bravo CPG, Turnkey vs Non-Turnkey (Tolling): Which Manufacturing Model Is Actually Right for Your Brand?
Read Nov 28, 2026. The views quoted are the authors’.
Cannot tell which model your quote assumes?
Email the quote to ben@genwest.ventures. The Co-Pack Quote & Contract Review is available starting at $1,500. Price is set before we start, based on what you send.
Not legal advice. We work alongside your attorney, and we will recommend one if you do not have one.
We treat submitted project information as confidential, as stated in our Terms.
Contract terms · How to read a co-packer quote · Launch costs · RFP template · Co-packer RFP checklist · Co-packer sourcing · Co-pack quote review · Back to the home page